Construction Updates
 
 

Travis Elementary School Project Scope of Work

  1. Improve electrical service and add outlets at existing classrooms
  2. Renovate the administration area
  3. Replace ceiling tiles in most classrooms and library
  4. Replace roof
  5. Renovate HVAC system to meet new ASHRAE standards
  6. Renovate clinic and restroom
  7. Furnish additional staff restrooms
  8. Renovate library
  9. Construct a building access ramp at the bus drop-off area
  10. Replace asbestos floor tile
  11. Renovate storage areas at the stage
  12. Renovate stage access to meet ADA
  13. Replace casement windows throughout school
  14. Renovate existing restrooms to meet ADA
  15. Renovate drinking fountains to meet ADA
  16. Install fully automatic fire sprinkler system

Current Activity

Project is complete.

 
     
 
Lamar CISD Project Photos
 
 
   <b></b>   
Travis Elementary School
Page: 1 2 Next
 Sort By  
Toilet 2 (3) (8/29/06)
   <br>
  
new class (8/29/06)
   <br>
  
new window in auditorium (8/29/06)
   <br>
  
Toilet entry (8/29/06)
   <br>
  
exterior view (3) (8/29/06)
   <br>
  
exterior view (4) (8/29/06)
   <br>
  
Toilet 2 (1) (8/29/06)
   <br>
  
door frame ready to be installed (8/1/06)
   <br>
  
installing new floor (8/1/06)
   <br>
  
building window (8/1/06)
   <br>
  
New AC inside class (8/1/06)
   <br>
  
Installing floor tile (8/1/06)
   <br>
  
toilet tile (8/1/06)
   <br>
  
digging utility trench (8/1/06)
   <br>
  
floor ready for tile (8/1/06)
   <br>
  
new glass block window (8/1/06)
   <br>
  
New Floor (6/21/06)
   <br>
  
Work on roof 2 (7/21/06)
   <br>
  
work in hall 2 (7/21/06)
   <br>
  
Work in assembly room (7/21/06)
   <br>
  
New Wall (7/21/06)
   <br>
  
Contractor equip (7/21/06)
   <br>
  
Painted cabinets (7/21/06)
   <br>
  
New Structural frame (7/21/06)
   <br>
  
Repair of Roof (7/21/06)
   <br>
  
New Plumbing riser (06/29/06)
   <br>
  
New slab (7/06/06)
   <br>
  
Asphalt for new roof (06/23/06)
   <br>
  
new exterior wall (7/06/06)
   <br>
  
getting ready for slab (7/06/06)
   <br>
  
More walls ready to be installed (06/23/06)
   <br>
  
New ac duct (7/06/06)
   <br>
  
Stored materials (7/6/06)
   <br>
  
New fire sprinkler head (06/29/06)
   <br>
  
New exterior wall2 (07/6/06)
   <br>
  
New sturctural beam at office (06/23/06)
   <br>
  
New plumbing lines (06/23/06)
   <br>
  
New Walls (06/29/06)
   <br>
  
Comm cable (06/23/06)
   <br>
  
Fire system in Kitchen (06/29/06)
   <br>
  
Fire pipe to be installed (06/23/06)
   <br>
  
Remove water fountain (7/6/06)
   <br>
  
ceiling work3 (7/6/06)
   <br>
  
Ready for new conc (7/06/06)
   <br>
  
Rebar mat for new const (06/23/06)
   <br>
  
New ducts 2 (07/06/06)
   <br>
  
New wing under construction (06/29/06)
   <br>
  
Mechanical rm (7/06/06)
   <br>
  
New AC ducts (06/29/06)
   <br>
  
Work in hall ceiling (06/29/06)
   <br>
  
New ducts in class (06/29/06)
   <br>
  
New cement (06/23/06)
   <br>
  
Laying out fire system (06/29/06)
   <br>
  
Remediation isolation (06/15/06)
   <br>
  
Demolition at Plmg (06/15/06)
   <br>
  
Work in Hall (06/15/06)
   <br>
  
New Pipe for fire system (06/15/06)
   <br>
  
Roof work (06/15/06)
   <br>
  
New Ceiling grid (06/15/06)
   <br>
  
New Fire line in clg (06/15/06)
   <br>
  
Ceiling Work (06/15/06)
   <br>
  
Digging foundation (06/15/06)
   <br>
  
Fire system fittings (06/15/06)
   <br>
  
Work on new classes (06/15/06)
   <br>
  
Class demolition (06/15/06)
   <br>
  
Saw Cut Conc (06/15/06)
   <br>
  
Class (06/09/06 )
   <br>
  
demolition (06/08/06)
   <br>
  
Work on MECH system (06/09/06)
   <br>
  
Clg demo (06/08/06)
   <br>
  
Office area demo (06/08/06)
   <br>
  
Hall (06/09/06)
   <br>
  
demo at front door (06/08/06)
   <br>
  
hal (06/08/06)
   <br>
  
Window replacement (06/08/06)
   <br>
  
Page: 1 2 Next