Beasley Elementary School Project Scope of Work
- Upgrade HVAC system to meet new ASHRAE standards
- Furnish fire alarm system
- Construct walls and doors to enclose open concept systems
- Furnish additional ADA parking spaces
- Renovate clinic restroom to meet ADA standards
- Furnish an isolation room in the clinic
- Repair roof
- Renovate restrooms to meet ADA standards
- Renovate stage to meet ADA standards
- Replace HVAC boiler
- Furnish an automatic fire sprinkler system throughout the building

Project Highlights
-
SHW presented schematic design / design development at the November School Board meeting.
-
Technology Review meeting is scheduled for December 5.
-
Design Committee meeting is scheduled for December 6.
-
70% Construction Documents are scheduled to be delivered for review on December 6.
-
Preliminary specifications for asbestos abatement have been received

Current Activity
Project is complete. |
|
|
|
| |
|
|
|
|